TL;DR: Two local clearances usually come before the mayor’s permit. The locational clearance, issued by the city or municipal planning office, confirms your activity fits the zoning at your address. The sanitary permit, issued by the city or municipal health office, is mandatory for food establishments under national law and is required for many other businesses under local tax codes.
What the locational clearance confirms
A locational clearance answers one question: can this activity operate at this address? Mandaluyong’s City Planning and Development Department describes its Locational Clearance for business permits as “a clearance issued by the CPDD - Zoning Division which determines whether a proposed business conforms” with the existing land use plan of the city. The page names Ordinance Nos. 664 (2017) and 756 (2020) as the zoning ordinance it applies.
It does not register your company, issue a permit, or approve construction. It is a land use finding that other offices rely on.
Other LGUs use different names. Mandaluyong’s guidelines call it a zoning clearance, and some cities call it a certificate of zoning compliance. Ask the planning office which document it issues for your activity.
Who issues each clearance
- Locational or zoning clearance: the city or municipal planning and development office. In Mandaluyong, the Zoning Division of the City Planning and Development Department. Its guidelines tell new applicants to “secure a Zoning Clearance from the City Planning and Development Office,” and list several named malls as exempt.
- Sanitary permit: the city or municipal health office. PD 856 uses the phrase “local health office.” Angono’s Municipal Health Office lists its service as a “Sanitary Permit to Operate.”
Why the address must match the zoning classification
Each LGU’s land use plan assigns areas to uses such as residential, commercial, or industrial. The locational clearance tests your proposed activity against the zone where the premises sit. A foreign founder who signs a lease first and checks zoning later can end up with a location that cannot host the business.
Mandaluyong’s step list puts the zoning clearance before the mayor’s permit is claimed. An address that does not fit its zone will stop the application at that step. The rule is simple, but the mismatch is often found late, after the lease and fit-out are already paid for.
The fee rules make the point. Mandaluyong’s page says a surcharge of 100% of the locational clearance fees, with a minimum of ₱2,000, applies to anyone who starts a project without first securing the clearance.
What the sanitary permit covers
PD 856, the Code on Sanitation of the Philippines, is dated December 23, 1975. Its key rule for permits is Section 14(a): “No person or entity shall operate a food establishment for public patronage without securing a permit from the local health office.”
That is the national mandate, and it names food establishments. It does not, in that section, require a sanitary permit for every office. Two other sources reach further:
- RA 11032, the Ease of Doing Business Act, Section 11(d): “To lessen the transaction requirements, other local clearances such as, but not limited to, sanitary permits, environmental and agricultural clearances shall be issued together with the business permit.”
- Mandaluyong’s Revised Business Tax Code, Section 121: every owner or operator of “business, industrial, commercial or agricultural establishments” must secure a sanitary certificate or permit by paying an annual fee to the City Treasurer.
So for a professional office, the requirement usually sits in your city’s tax code, not in PD 856. Mandaluyong’s Section 121 fees depend on the type and floor area of the business. The page lists ₱110.00 for “administration offices, display offices, and professionals’ offices” (the page omits the currency symbol on that line), and by floor area for other businesses: under 50 square meters 110.00, 50 to under 100 square meters 220.00, 100 to under 200 square meters 330.00, 200 to under 500 square meters 440.00, 500 to under 1,000 square meters 660.00, and 1,000 square meters or more 880.00. Where one owner runs two or more businesses in one place, the page says the fee follows the business with the highest rate.
Angono’s municipal page for the same permit lists one requirement, an “Official Receipt of Payment,” names the Municipal Health Office as the issuer, and says the fee “varies according to assessment of the business.” It gives a processing time of “1 hour and 8 minutes.” A single municipality’s page does not show the full checklist for a city, so treat it as one example.
Health certificates for food handlers
Section 19(a) of PD 856 says: “No person shall be employed in any food establishment without a health certificate issued by the local health authority.” Section 2(e) defines the local health authority as an official or employee responsible for applying a prescribed health measure in a local political subdivision.
This applies to people who work in a food establishment. It does not reach ordinary office staff under that section. Mandaluyong’s guidelines add a separate step: food businesses, and businesses that need an Environmental Compliance Certificate, must have their forms “registered and stamped at the City Health Office.” For a new business, the page says this applies to manufacturers, gasoline stations, warehouses, eateries, restaurants, and similar establishments.
Section 103(a) makes a violation of the Code’s rules a misdemeanor, punishable by imprisonment of not more than six months, a fine of not more than ₱1,000, or both, as the decree is written.
What the LGU checklists ask for
Requirements differ by city. Three examples from city pages:
Mandaluyong, locational clearance for business. The CPDD page summarizes the requirements as a notarized application form, copies of the title, tax declaration, barangay clearance, and lease documents if applicable, and colored photos of the inside and outside of the location. Depending on the zone, the page adds neighbor consent within a 50-meter radius, a homeowners’ association clearance, or an Environmental Compliance Certificate. The same page gives a filing fee of ₱200.25, a land use fee of ₱6.75 per square meter of floor area for commercial use, a processing charge of 25% of the land use fee, and a certificate charge of ₱104.18. It states processing as “about 5 minutes plus 3 to 6 hours in total.”
Quezon City, business permit renewal. The page lists an official receipt of the current year’s business tax from the City Treasurer’s Office, a barangay business clearance if already secured, the previous business permit, and an authorization form if a representative files. It does not list a sanitary permit, a zoning clearance, or a fire certificate. Renewal is filed “one (1) year from the issuance date” of the permit.
Angono, sanitary permit. Described above: one listed requirement, a variable fee, and a stated processing time.
The gap between the Quezon City list and the Mandaluyong list is the point. Ask the business permit office for the current checklist for your address before you assume either one applies. The business permit renewal guide covers the annual cycle these clearances feed into.
Where these fit in the one-stop shop
RA 11032 defines the Business One-Stop Shop (BOSS) in Section 4(b) as “a single common site or location, or a single online website or portal” for an LGU’s business permit and licensing system. Section 11(a) requires a unified application form that brings together information from several departments, including taxes, building, sanitary, zoning, and fire clearances. Section 11(b) requires the BOSS to co-locate the treasury, the business permits and licensing office, the zoning office, and the Bureau of Fire Protection. Section 12(g) says the BFP must collocate with the BOSS or in an area the city or municipality designates.
The statute names zoning and sanitary clearances. It does not name the locational clearance, so check which office in your city issues the zoning document.
In practice, Quezon City’s online route is a BOSS menu. The renewal page tells applicants to select “Business One-Stop Shop,” then “Apply for Mayor’s Permit (Business),” then “Submit Application Online,” then “Renewal.” The page does not explain where the zoning or sanitary steps sit inside that flow.
Mandaluyong’s guidelines describe a sequential in-person process at its Business Permits and Licensing Office, and the page does not mention a one-stop shop. Its new-business steps run: submit the notarized form, obtain the zoning clearance, endorse for fee assessment, get the health office stamp if applicable, pay the tax order, pay the fire fee at the treasurer, then claim the permit.
Step order for a new business
Use Mandaluyong’s order as the working sequence, and confirm it with your city:
- Get the barangay business clearance for the premises.
- Apply for the locational or zoning clearance at the planning office.
- Ask the health office whether a stamp or sanitary permit applies to your activity.
- Submit the notarized application and documents to the business permits office for assessment.
- Pay the local tax order and the fire fee, then claim the mayor’s permit.
Common mistakes foreign-owned companies make
- Signing a lease before checking zoning. The lease is part of the clearance file, but the zoning check decides whether the activity can run there at all. Starting before the clearance carries the surcharge described above.
- Treating sanitary as a restaurant-only issue. For food businesses PD 856 is the national rule. For other businesses, check your city’s tax code, since Mandaluyong’s Section 121 applies its sanitary fee to every business establishment.
- Using one city’s checklist for another. Quezon City’s renewal list is short and omits the sanitary and zoning items that appear in Mandaluyong’s guidance.
- Assuming a virtual office address clears zoning. Confirm with the planning office that a virtual office address satisfies the locational clearance. The Mandaluyong checklist asks for the title or tax declaration, lease documents, and photos of the location. Ask the planning office about your specific address before you pay for it. The virtual office guide covers the registration side.
Next step
Before you sign a lease, send Chamberlain the address and the business activity. We can help you list the zoning and health questions to put to the local planning and health offices, and which documents the business permits office will ask for. Start with the LGU business permit service. For the fire inspection that comes alongside these clearances, read the FSIC guide. If you are changing an address you already registered, see the change of registered address guide.
Frequently asked questions
What is a locational clearance in the Philippines?
It is the local government's check that a proposed business fits the zoning and land use plan at its address. Mandaluyong's City Planning and Development Department issues its version as a Locational Clearance for business permits. Other cities may call it a zoning clearance or certificate of zoning compliance.
Who issues the sanitary permit?
The city or municipal health office. Section 14(a) of PD 856 requires the permit for food establishments. Many LGUs also require a sanitary certificate for other businesses under their own tax codes, so check your city's rules for an office.
Do office employees need health certificates?
Section 19(a) of PD 856 requires a health certificate for people employed in a food establishment. That section does not extend that requirement to ordinary office staff. Local rules can differ, so ask the health office.
Can a virtual office address pass the locational clearance?
Confirm with the planning office whether a virtual office address can pass before you pay for one. Mandaluyong's clearance asks for the title or tax declaration, any lease, and colored photos of the inside and outside of the location.
Is the zoning clearance the same as the mayor's permit?
No. In Mandaluyong's step list the zoning clearance comes before the mayor's permit is claimed. It confirms the location and activity fit the zone. The permit is the license to operate issued after the other offices assess and approve the application.
Official sources
Primary references this guide is checked against.
- Lawphil: Presidential Decree No. 856, Code on Sanitation of the Philippines (1975)
- Lawphil: Republic Act No. 11032, Ease of Doing Business and Efficient Government Service Delivery Act (2018)
- City of Mandaluyong: City Planning and Development Department
- City of Mandaluyong: Business applications guidelines
- City of Mandaluyong: Revised Business Tax Code, sanitary and health fees
- Quezon City: How to renew business permit
- Municipality of Angono: Municipal Health Office, sanitary permit to operate
Related guides
Business Permit Davao City: Requirements and Steps
How a new corporation gets a business permit in Davao City: the Business Bureau checklist, online steps, the Mayor's Permit fee basis and the January renewal.
Business Permit Quezon City: Steps and Requirements
How a new corporation gets a business permit in Quezon City: BPLD documents, QC E-Services filing, the city's business tax dates, and renewal rules.
Business Permit Pasig: Requirements and Steps
How a new company gets a business permit in Pasig: the barangay clearance, Certificate of Conformance, BPLD documents, payment, and release steps.